Run ID: gw-forecast-production-001-loop02
Status: task_complete
# North Star: Investment-Grade GW Forecast vs Actual
## Mission
Build **production-grade research** we can trust for **investment decisions** on whether **more gigawatts (GW) of data-center / AI infrastructure capacity are coming online** — past, present, and future.
For each of **17 target companies**, answer:
1. **What did they say?** — GW forecasts, pipeline, and guidance each quarter
2. **How did forecasts change?** — vintage panel: Oracle said X GW in Q1, revised to Y in Q3
3. **What actually happened?** — delivered / operating / under-construction GW vs the original forecast
4. **Can we see it on a chart?** — one **line graph per company** + one **portfolio line graph**
Example: *"Oracle said they'll have X data centers / Y GW by 2027. Each quarter we capture that statement. We track how the forecast moved quarter-to-quarter and compare the first forecast to what ultimately landed."*
## Target Companies (17)
ORCL, MSFT, AMZN, GOOGL, META, CoreWeave (CRWV), DLR, EQIX, IRM, APLD, CORZ, IREN, WULF, CIFR, HUT, NBIS/Nebius, NVDA
*(Vertiv/Eaton dropped from v1 — infrastructure suppliers, not capacity owners.)*
## Core Metrics (GW-first)
- operating / live GW (actual)
- GW under construction (actual snapshot)
- GW pipeline / future capacity (forecast)
- GW added this quarter (actual)
- forecast vintage: `as_of_quarter` → `target_period` → `forecast_gw`
- capex actuals & guidance (supporting evidence)
- revenue conversion per MW/GW where disclosed
## Canonical Output Layout
All production artifacts live under `research_loop/production/`:
```
production/
{TICKER}/
source_manifest.csv
forecast_vintage.csv # how forecasts changed each quarter
capacity_timeseries.csv # actual vs latest vs original forecast by period
company_gw_chart.html # line chart for this company
extractor.py
validator.py
portfolio_gw_timeseries.csv
portfolio_gw_chart.html
goal_progress.json # machine-readable completion status
```
## Done When (`north_star.json`)
- Every company has ≥8 quarters in `forecast_vintage.csv` and `capacity_timeseries.csv`
- Every company has provenance-complete rows (https source URLs, snippets, validation PASS)
- Every company has `company_gw_chart.html`
- Portfolio chart aggregates all companies
- `goal_completion.py` reports ≥85% investment-confidence score
## Source Preference
Primary: SEC 10-Q/10-K/8-K, earnings supplements, IR pages, investor decks, transcripts
Secondary: industry press (discovery only — not row-level evidence)
## Supervisor Mandate
The auto-continue supervisor runs **until the north star is achieved**, not for a fixed loop count. Each child loop picks **one company or one repair task** that moves the portfolio closest to done.
(none)
goal_progress.json sets next_priority_ticker=ORCL (0/17 complete, 74.7% confidence). Loop01 passed machine gate with real ORCL manifest+extractor+vintage (16 rows, 8 as-of periods) but nothing is promoted to production/ORCL/; capacity_timeseries.csv is falsely credited via eqix_rows.csv fallback. No blocked_reason or machine-gate failure in loop02. Finishing ORCL's remaining pipeline steps (timeseries → chart → validator) is the highest-leverage path to the first complete company and unlocks the portfolio-aggregation gate.
Status: passed
Review cycles: 2
| Time | Iter | Role | Task | Verdict | Decisions | Blockers | Artifacts |
|---|---|---|---|---|---|---|---|
| 2026-06-07T15:48:48.534171+00:00 | 0 | system | start | [ "run started" ] | [] | ||
| 2026-06-07T15:50:51.110099+00:00 | 1 | planner | Complete ORCL production gates: copy loop01 machine-gate PASS artifacts (source_manifest.csv, extractor.py, forecast_vintage.csv) into production/ORCL/, then derive capacity_timeseries.csv from the vintage panel (≥8 fiscal quarters: FY2024-FQ4 through FY2026-FQ3), build company_gw_chart.html plotting capex-actual vs latest/original FY2026 capex-guidance vintages (USD billions proxy — normalized_gw blank per Oracle non-disclosure), and add validator.py enforcing schema, ≥8 quarter rows, https provenance, and snippet integrity. Do not use EQIX/DLR fallback rows. | [ "goal_progress.json sets next_priority_ticker=ORCL (0/17 complete, 74.7% confidence). Loop01 passed machine gate with real ORCL manifest+extractor+vintage (16 rows, 8 as-of periods) but nothing is promoted to production/ORCL/; capacity_timeseries.csv is falsely credited via eqix_rows.csv fallback. No blocked_reason or machine-gate failure in loop02. Finishing ORCL's remaining pipeline steps (timeseries \u2192 chart \u2192 validator) is the highest-leverage path to the first complete company and unlocks the portfolio-aggregation gate." ] | [] | ||
| 2026-06-07T15:54:34.846288+00:00 | 1 | worker | Complete ORCL production gates: copy loop01 machine-gate PASS artifacts (source_manifest.csv, extractor.py, forecast_vintage.csv) into production/ORCL/, then derive capacity_timeseries.csv from the vintage panel (≥8 fiscal quarters: FY2024-FQ4 through FY2026-FQ3), build company_gw_chart.html plotting capex-actual vs latest/original FY2026 capex-guidance vintages (USD billions proxy — normalized_gw blank per Oracle non-disclosure), and add validator.py enforcing schema, ≥8 quarter rows, https provenance, and snippet integrity. Do not use EQIX/DLR fallback rows. | [ "## Decisions", "- **Promoted loop01 PASS artifacts unchanged** for `source_manifest.csv`, `forecast_vintage.csv`, and `extractor.py` (19 manifest sources, 16 vintage rows, 8 `as_of_period` vintages, live SEC/IR fetch + call-snippet guidance chain).", "- **USD capex proxy, not GW:** Oracle does not disclose MW/GW; all `normalized_gw` / GW timeseries columns are blank. `capacity_timeseries.csv` uses `capex_actual_usd_b` and `capex_guidance_*_usd_b` as investment proxies.", "- **Timeseries rollup logic:** Quarterly `capex_actual` rows map directly; FY2025-FQ4 Q4 derived from annual minus Q1\u2013Q3; FY2026 quarters derived from YTD (`capex_actual_ytd`) deltas. Latest FY2026 guidance rolls forward by `as_of_period` (blank before FY2025-FQ4); original fixed at **25** (first vintage, FY2025-FQ4 \u201c>$25B\u201d).", "- **Chart:** Self-contained SVG/HTML with three series (capex actual, latest guidance vintage, original guidance) plus visible GW-proxy banner.", "- **Validator:** Enforces schema, \u226516 vintage / \u22658 timeseries rows, https provenance, `verified_primary` snippet sampling, guidance revision spot-checks, and live extractor re-run (16 rows). No EQIX/DLR fallbacks.", "## Evidence", "**PRIMARY**" ] | [ "Artifact artifacts/extractor.py is too short (339 chars)" ] | capacity_timeseries.csv, company_gw_chart.html, extractor.py, forecast_vintage.csv, production/ORCL/build_timeseries.py, production/ORCL/capacity_timeseries.csv, production/ORCL/company_gw_chart.html, production/ORCL/extractor.py, production/ORCL/forecast_vintage.csv, production/ORCL/source_manifest.csv, production/ORCL/validator.py, source_manifest.csv, validator.py | |
| 2026-06-07T15:57:15.195695+00:00 | 1 | fixer | Complete ORCL production gates: copy loop01 machine-gate PASS artifacts (source_manifest.csv, extractor.py, forecast_vintage.csv) into production/ORCL/, then derive capacity_timeseries.csv from the vintage panel (≥8 fiscal quarters: FY2024-FQ4 through FY2026-FQ3), build company_gw_chart.html plotting capex-actual vs latest/original FY2026 capex-guidance vintages (USD billions proxy — normalized_gw blank per Oracle non-disclosure), and add validator.py enforcing schema, ≥8 quarter rows, https provenance, and snippet integrity. Do not use EQIX/DLR fallback rows. | [ "mechanical fix pass 1" ] | [] | capacity_timeseries.csv, company_gw_chart.html, extractor.py, forecast_vintage.csv, production/ORCL/build_timeseries.py, production/ORCL/capacity_timeseries.csv, production/ORCL/company_gw_chart.html, production/ORCL/extractor.py, production/ORCL/forecast_vintage.csv, production/ORCL/source_manifest.csv, production/ORCL/validator.py, source_manifest.csv, validator.py | |
| 2026-06-07T15:59:21.689714+00:00 | 1 | reviewer | Complete ORCL production gates: copy loop01 machine-gate PASS artifacts (source_manifest.csv, extractor.py, forecast_vintage.csv) into production/ORCL/, then derive capacity_timeseries.csv from the vintage panel (≥8 fiscal quarters: FY2024-FQ4 through FY2026-FQ3), build company_gw_chart.html plotting capex-actual vs latest/original FY2026 capex-guidance vintages (USD billions proxy — normalized_gw blank per Oracle non-disclosure), and add validator.py enforcing schema, ≥8 quarter rows, https provenance, and snippet integrity. Do not use EQIX/DLR fallback rows. | PASS | [ "review cycle 1" ] | [] | capacity_timeseries.csv, company_gw_chart.html, extractor.py, forecast_vintage.csv, production/ORCL/build_timeseries.py, production/ORCL/capacity_timeseries.csv, production/ORCL/company_gw_chart.html, production/ORCL/extractor.py, production/ORCL/forecast_vintage.csv, production/ORCL/source_manifest.csv, production/ORCL/validator.py, source_manifest.csv, validator.py |
| 2026-06-07T15:59:21.710421+00:00 | 1 | machine_gate | Complete ORCL production gates: copy loop01 machine-gate PASS artifacts (source_manifest.csv, extractor.py, forecast_vintage.csv) into production/ORCL/, then derive capacity_timeseries.csv from the vintage panel (≥8 fiscal quarters: FY2024-FQ4 through FY2026-FQ3), build company_gw_chart.html plotting capex-actual vs latest/original FY2026 capex-guidance vintages (USD billions proxy — normalized_gw blank per Oracle non-disclosure), and add validator.py enforcing schema, ≥8 quarter rows, https provenance, and snippet integrity. Do not use EQIX/DLR fallback rows. | CHANGES_REQUIRED | [ "machine validation failed after reviewer PASS" ] | [ "source manifest missing column: metrics_supported", "source manifest missing column: caveat" ] | capacity_timeseries.csv, company_gw_chart.html, extractor.py, forecast_vintage.csv, production/ORCL/build_timeseries.py, production/ORCL/capacity_timeseries.csv, production/ORCL/company_gw_chart.html, production/ORCL/extractor.py, production/ORCL/forecast_vintage.csv, production/ORCL/source_manifest.csv, production/ORCL/validator.py, source_manifest.csv, validator.py |
| 2026-06-07T16:02:42.231430+00:00 | 1 | fixer | Complete ORCL production gates: copy loop01 machine-gate PASS artifacts (source_manifest.csv, extractor.py, forecast_vintage.csv) into production/ORCL/, then derive capacity_timeseries.csv from the vintage panel (≥8 fiscal quarters: FY2024-FQ4 through FY2026-FQ3), build company_gw_chart.html plotting capex-actual vs latest/original FY2026 capex-guidance vintages (USD billions proxy — normalized_gw blank per Oracle non-disclosure), and add validator.py enforcing schema, ≥8 quarter rows, https provenance, and snippet integrity. Do not use EQIX/DLR fallback rows. | [ "machine-gate fix cycle 1" ] | [] | capacity_timeseries.csv, company_gw_chart.html, extractor.py, forecast_vintage.csv, production/ORCL/build_timeseries.py, production/ORCL/capacity_timeseries.csv, production/ORCL/company_gw_chart.html, production/ORCL/extractor.py, production/ORCL/forecast_vintage.csv, production/ORCL/source_manifest.csv, production/ORCL/validator.py, source_manifest.csv, validator.py | |
| 2026-06-07T16:04:45.353999+00:00 | 1 | reviewer | Complete ORCL production gates: copy loop01 machine-gate PASS artifacts (source_manifest.csv, extractor.py, forecast_vintage.csv) into production/ORCL/, then derive capacity_timeseries.csv from the vintage panel (≥8 fiscal quarters: FY2024-FQ4 through FY2026-FQ3), build company_gw_chart.html plotting capex-actual vs latest/original FY2026 capex-guidance vintages (USD billions proxy — normalized_gw blank per Oracle non-disclosure), and add validator.py enforcing schema, ≥8 quarter rows, https provenance, and snippet integrity. Do not use EQIX/DLR fallback rows. | PASS | [ "review cycle 2" ] | [] | capacity_timeseries.csv, company_gw_chart.html, extractor.py, forecast_vintage.csv, production/ORCL/build_timeseries.py, production/ORCL/capacity_timeseries.csv, production/ORCL/company_gw_chart.html, production/ORCL/extractor.py, production/ORCL/forecast_vintage.csv, production/ORCL/source_manifest.csv, production/ORCL/validator.py, source_manifest.csv, validator.py |
| 2026-06-07T16:04:45.382843+00:00 | 1 | machine_gate | Complete ORCL production gates: copy loop01 machine-gate PASS artifacts (source_manifest.csv, extractor.py, forecast_vintage.csv) into production/ORCL/, then derive capacity_timeseries.csv from the vintage panel (≥8 fiscal quarters: FY2024-FQ4 through FY2026-FQ3), build company_gw_chart.html plotting capex-actual vs latest/original FY2026 capex-guidance vintages (USD billions proxy — normalized_gw blank per Oracle non-disclosure), and add validator.py enforcing schema, ≥8 quarter rows, https provenance, and snippet integrity. Do not use EQIX/DLR fallback rows. | PASS | [ "expected artifact validators and production gates passed" ] | [] | capacity_timeseries.csv, company_gw_chart.html, extractor.py, forecast_vintage.csv, production/ORCL/build_timeseries.py, production/ORCL/capacity_timeseries.csv, production/ORCL/company_gw_chart.html, production/ORCL/extractor.py, production/ORCL/forecast_vintage.csv, production/ORCL/source_manifest.csv, production/ORCL/validator.py, source_manifest.csv, validator.py |
Generated 2026-06-07T16:04:45.483274+00:00